9- "Shoeibie Main Canal and Protective Dike". |
| 9- "Shoeibie Main Canal and Protective
Dike". |
| Description: |
| Designing, and construction supervision
of "Shoeibie Main Canal 37 km,
Main Drain 24 km, and Protective Dike
7.5 km". |
 |
|
| Stage
of Design: |
I, II, III |

Click to enlarge! |
| Client: |
Ministry of Agriculture |
| Area
(hectares): |
18,000 |
| Location: |
Khoozastan
|
| Rate
of Progress: |
100% |
| Date
of Start: |
Feb. 1995 |
| Date
of End: |
Mar. 1999 |
Completed
Cost
(106 Rials):
|
30,000 |
|
|
10- "Karun-river Pump Station & Transmission
Pipelines". |
| 10- "Karun-river Pump Station &
Transmission Pipelines". |
| Description: |
| Designing, and supervision of water
pumping station from Karun-river, with
capacity of 25 m3/sec and also 5 transmission
pipelines with steel pipes (diameter.
1400 mm, length: 2360 m) . |
 |
|
| Stage
of Design: |
I, II, III |

Click to see more! |
| Client: |
Ministry of Agriculture |
| Area
(hectares): |
14,000 |
| Location: |
Khoozastan
|
| Rate
of Progress: |
100% |
| Date
of Start: |
Nov. 1996 |
| Date
of End: |
Aug. 1998 |
Completed
Cost
(106 Rials):
|
6,700
+ $6,000,000 |
|
| 11-
"Zangane Irrigation & Drainage Network". |
| 11- "Zangane Irrigation & Drainage
Network". |
| Description: |
| Construction supervision of third
part of "Zangane Irrigation &
Drainage Network" . |
 |
|
| Stage
of Design: |
III |

Click to enlarge! |
| Client: |
Ministry of Energy |
| Area
(hectares): |
1,500 |
| Location: |
West
Azarbayjan |
| Rate
of Progress: |
100% |
| Date
of Start: |
Dec. 1993 |
| Date
of End: |
Feb. 2001 |
Completed
Cost
(106 Rials):
|
13,800 |
|
| 12-
"Zangane Irrigation & Drainage Network
- 1st part - Construction Supervision" . |
| 12- "Zangane Irrigation & Drainage
Network - 1st part - Construction Supervision"
. |
| Description: |
| Construction supervision of first
part of "Zangane Irrigation &
Drainage Network" . |
 |
|
| Stage
of Design: |
III |
Click to enlarge! |
| Client: |
Ministry of Energy |
| Area
(hectares): |
750 |
| Location: |
West
Azarbayjan |
| Rate
of Progress: |
100% |
| Date
of Start: |
Dec. 1993 |
| Date
of End: |
May. 2001 |
Completed
Cost
(106 Rials):
|
10,000 |
|
| 13-
"Shoeibie Sugar Cane Agro-industry - Water
Supply and Runoff Discharge Network " . |
| 13- "Shoeibie Sugar Cane Agro-industry
- Water Supply & Runoff Discharge Network
" |
| Description: |
| Designing, and construction supervising
of water supply and runoff discharge
network for industrial part of "Shoeibie
Sugar Cane Agro-industry" . |
 |
|
| Stage
of Design: |
I, II, III |

|
| Client: |
Ministry of Agriculture |
| Location: |
Khoozastan
|
| Rate
of Progress: |
100% |
| Date
of Start: |
Dec. 1997 |
| Date
of End: |
Sep. 1998 |
Completed
Cost
(106 Rials):
|
2,500 |
|
| 14-
"Shoeibie Sugar Cane Agro-industry - 3rd Part"
. |
| 14- "Shoeibie Sugar Cane Agro-industry
- 3rd Part". |
| Description: |
| Construction supervision of third
part of "Shoeibie Sugar Cane Agro-industry"
. |
 |
|
| Stage
of Design: |
III |

Click to enlarge! |
| Client: |
Ministry of Agriculture |
| Area
(hectares): |
9,500 |
| Location: |
Khoozastan
|
| Rate
of Progress: |
100% |
| Date
of Start: |
Apr. 1995 |
| Date
of End: |
Feb. 2000 |
Estimated
Cost
(106 Rials):
|
32,000 |
|
| 15-
"Sugare Cane Railway Transportation". |
| 15- "Sugare Cane Railway Transportation". |
| Description: |
| Designing and supervision of infrastructure
of railway for transporting the sugar
cane |
 |
|
| Stage
of Design: |
I, II, III |

|
| Client: |
Ministry of Agriculture |
| Area
(hectares): |
18,000 |
| Location: |
Khoozastan
|
| Rate
of Progress: |
100% |
| Date
of Start: |
Jul. 1995 |
| Date
of End: |
Mar. 2001 |
Estimated
Cost
(106 Rials):
|
4,250 |
|
| 16-
"Basic Criteria of Agricultural Development". |
| 16- "Basic Criteria of Agricultural
Development". |
| Description: |
| Defining of guidelines for agricultural
norms and standards. |
 |
|
| Stage
of Design: |
I |

|
| Client: |
Ministry of Agriculture |
| Area
(hectares): |
All the country
|
| Location: |
All
the country |
| Rate
of Progress: |
100% |
| Date
of Start: |
Jul. 1995 |
| Date
of End: |
Sep. 1999 |
|
|
17- "Shahr-Chai Irrigation and Drainage Network"
. |
| 17- "Shahr-Chai Irrigation and Drainage
Network" . |
| Description: |
| Studying, and designing of "Shahre-Chai,
Irrigation & Drainage Network"
|
 |
|
| Stage
of Design: |
I |

Click to see more! |
| Client: |
Ministry of Energy |
| Area
(hectares): |
15,600 |
| Location: |
West
Azarbayjan |
| Rate
of Progress: |
100% |
| Date
of Start: |
Nov. 1996 |
| Date
of End: |
Mar.
1999 |
Estimated
Cost
(106 Rials):
|
70,000 |
|
| 18-
"Marvast Reservoir Dam & Groundwater Survey". |
| 18- "Marvast Reservoir Dam & Groundwater
Survey". |
| Description: |
| "Studying, and designing of
"Marvast Reservoir- dam with Hydrogeology
Surveying and Mathematical Modelling
of Groundwater" for various districts
of Yazd province. |
 |
|
| Stage
of Design: |
I |

|
| Client: |
Ministry of Energy |
| Location: |
Yazd |
| Rate
of Progress: |
100% |
| Date
of Start: |
Mar. 1997 |
| Date
of End: |
Oct. 2000 |
Estimated
Cost
(106 Rials):
|
90,000 |
|
|
|